To safely carry the loads of the Techno Steel Processing Turkey Building, the Application of a total of 2540 m of plastic piles with a diameter of Ø80 cm and 1800 m of sub-foundation bored piles with a diameter of Ø65 cm was carried out.
To verify the bearing capacity and settlement performance of the system, 2 axial pile load tests were performed at the end of the manufacturing process; in light of the obtained data, the compliance of the productions with TBDY 2018 and project design criteria was technically reported.
Services given:
Applications: