HSM Cankiri

HSM Cankiri


PROJECT INFO

Project:
HSM Cankiri Sumitomo Tire Factory Unit 3 Production Facility Building Ground Improvement Project
Customer:
HSM İnşaat
Date:
2025
Location:
Cankırı, Merkez

In 2025, a ground improvement project was prepared to eliminate the settlement potential originating from uncontrolled fill at the Çankırı Sumitomo Tire Factory Unit 3 site. In this prepared design package; 1237 Mini DSM Columns with a diameter of Ø35 cm were designed to ensure settlement control under the slabs. Under sensitive machine foundations, to achieve high bearing capacity and rigidity, 133 Mini Piles with a diameter of Ø30 cm and 798 Mini Jet Grout Columns were designed in accordance with technical specifications and load analyses.

Services given:

Geotechnical Design

Applications: